An interior design payment schedule format for India has six columns: stage number, the trigger that makes the payment due, percentage, amount including GST, days to pay, and what the client receives at that point. A common shape is a booking amount, design sign-off, material procurement, work completion, handover and a small retention. The percentages are yours to negotiate; no single national standard fixes them.
Updated November 2026. Written for studio owners and design-and-execute firms. The figures below are examples.
Interior design payment schedule format you can copy
| Stage | Payment falls due when | Share | Client receives |
|---|---|---|---|
| 1. Booking | Agreement signed | 10% | Project slot, site measurement |
| 2. Design sign-off | Layouts and views approved in writing | 20% | Final drawings and material list |
| 3. Procurement | Boards, hardware and finishes ordered or delivered | 30% | Delivery note or order confirmation |
| 4. Execution | Carpentry and finishes installed | 25% | Joint site inspection |
| 5. Handover | Keys or site handed back | 10% | Snag list with fix dates |
| 6. Retention | Snags closed, or an agreed date | 5% | Closure confirmation |
Add one line under the table: payment is due within a stated number of days of the trigger, and work on the next stage starts after the current one is paid. Have a lawyer check any clause about stopping work, cancellation or late fees before you rely on it.
Worked example: a ₹9,00,000 fit-out
This is an illustration only. Assume a contract of ₹9,00,000 before tax. GST is taken at 18% purely to show the arithmetic, giving ₹10,62,000. The right rate, and whether design fees and execution should be billed differently, depends on your contract and registration, so confirm with your CA.
- Booking, 10%: ₹1,06,200
- Design sign-off, 20%: ₹2,12,400
- Procurement, 30%: ₹3,18,600
- Execution, 25%: ₹2,65,500
- Handover, 10%: ₹1,06,200
- Retention, 5%: ₹53,100
The six figures add back to ₹10,62,000. Now check cash flow, which most copied formats skip. Suppose boards, hardware and finishes will cost you ₹4,50,000. By the time you order, you have collected stages 1 to 3, which is ₹6,37,200 including GST, or ₹5,40,000 before tax. That leaves ₹90,000 before tax for design time and early labour. If your own version leaves that number negative, you are financing the client’s home, and the procurement share should go up or the order should be split.
Choosing the split: design-only, design-and-execute, or turnkey
- Design fee only. Fewer stages work better: booking, concept approval, final drawings. There is no material to fund, so a retention rarely makes sense.
- Design and execute. Use the six stages above. Keep the largest payments just before your largest purchases.
- Turnkey with several rooms or floors. Split execution by area, for example kitchen, wardrobes and living room, so one delayed area does not hold up the whole instalment.
Clauses that prevent stage-payment disputes
- A visible trigger. “Carpentry installed” is checkable. “50% progress” is not.
- Who confirms it. Name the person and the channel, such as a written message from the client.
- Days to pay. State the number, counted from the confirmation.
- Client-caused delay. Say what happens if the site, society permission or a client-supplied item is not ready.
- Variations. Extra work is quoted and accepted separately before it starts.
- Retention release. Give a latest date, not only a condition.
- Cancellation. Say how paid amounts are treated at each stage.
Raising each stage from one quotation in FINTY
Write the schedule into the Notes field of your quotation, then bill from that same record. The interior design quotation format is a starting layout for the itemised part.
- Send the quotation. Share a link where the client can view it and accept or decline.
- Press Advance / milestone. On an accepted quotation, enter a label such as “Design sign-off” and the amount including GST.
- Check the proforma. FINTY creates a draft proforma at the quotation’s effective GST rate, as a single line referring to the quotation. The due date starts at 30 days out, so change it to match your terms before sending.
- Mark it paid and convert it. A paid proforma converts into a tax invoice that keeps the proforma reference.
- Repeat for the next stage. The window shows quotation total, already invoiced and remaining, and will not let you bill more than what is left.
Two practical points. First, the 25%, 50% and 100% shortcut buttons in that window calculate on the remaining amount, not the contract total, so for the schedule above type the rupee figure. Second, the ageing report covers unpaid and part-paid tax invoices, not proformas. Keep an eye on sent proformas in the invoice list until they are paid. The single effective rate also matters if your quotation mixes GST rates: ask your CA whether to raise those stages as itemised invoices instead.
Try it on one live project: start free or use the 30-day trial, and compare plans on the pricing page.
Handling variations without breaking the schedule
Say the client adds a study unit worth ₹60,000 before tax after procurement. Leave the original six stages untouched. Send a second quotation for the unit, get it accepted, and bill it with its own advance and balance. The client can then see that the contract they signed has not changed, and you can see which money belongs to the extra work.
A five-minute weekly check
- For each live project, note the last trigger actually reached on site.
- Compare it with the amount already invoiced on that quotation.
- Raise anything reached but not billed the same day.
- Follow up on sent proformas and on overdue tax invoices.
- List retentions with their release dates.
Beyond the schedule
Billing is one part of a studio. Leads, follow-ups, team payroll and expense claims are covered in our guide to interior designer management software, and the FINTY page for interior designers gives the short overview. For the fields on each tax document, see the GST invoice format for interior designers. FINTY does not do bills of quantities, procurement workflows, drawings or site tracking.